Supreme Court Bans Construction Within 100 Metres Of Rajasthan's Johari River, Imposes 500-Metre No-Pollution Buffer

Supreme Court imposed interim safeguards around Rajasthan’s Johari river pending scientific determination of the High Flood Line and ecological buffer zones
The Supreme Court on Monday directed that no construction or development activity of any nature shall be permitted within 100 metres from the edge of the Jojari river in Rajasthan, pending scientific determination of the High Flood Line and ecological buffer zones.
As an additional interim safeguard, the Bench of Justices Vikram Nath and Sandeep Mehta also barred any hazardous industry or activity capable of causing pollution, contamination or other damage to the riverine ecosystem within 500 metres on either side of the existing flood line; wherever identified, or the river's present flow path.
The Court clarified that these restrictions will remain in force until the scientific exercise for determining and demarcating the High Flood Line and requisite ecological buffer zones is completed.
The bench also addressed concerns over the functioning of the committee constituted for the exercise, noting a substantial overlap between the committee and the Integrated Coordination Group, with several senior government functionaries serving on both bodies.
The Court clarified that the Integrated Coordination Group is merely an internal government arrangement for smooth coordination between departments and does not impinge upon the domain of the committee. However, it acknowledged that the overlapping membership could create practical difficulties in the independent and effective discharge of the two bodies' respective functions.
The Court clarified that the Chairperson of the committee, in his individual capacity, may, whenever necessary, issue suitable directions, orders and instructions to ensure effective and expeditious coordinated implementation of the Court's directions and the committee's mandate. Earlier directions empowering the committee to take necessary action and pass requisite orders will continue to operate in letter and spirit, the Court made clear.
The Court also passed directions concerning the assignment of the project to the National University, and considered the prayer seeking permission for release of the polluted accumulated water, issuing necessary directions in this regard.
The matter will be listed again on September 27.